Quincy Road Construction Updates

Published on May 23, 2025

Quincy Road Construction Updates.jpg
LIST OF CURRENT AND FUTURE ROAD CONSTRUCTION UPDATES 
Post Date:05/23/2025 12:00 PM

QUINCY ROAD CONSTRUCTION UPDATE
Current as of June 23, 2025

 

ACTIVE PROJECTS

1. Broadway Water Main Replacement ‐ 12th to 24th
• Location:               Broadway between 12th and 24th Streets
• Timeline:               April 11 ‐ August 15, 2025
• Traffic Impact:     One lane open in each direction
                                   North 18th scheduled to be closed week of July 28
Details: New water main, replacement of water service lines, some sidewalk replacement

2. North 22nd Reconstruction ‐ Broadway to Oak
• Location:               North 22nd from Broadway to Oak
• Timeline:               April 11 ‐ August 1, 2025
• Traffic Impact:     FULL CLOSURE
Details: New pavement, replacement of water main & water services, new sidewalks and driveways,
paving scheduled for the week of July 21.


3. Harrison Street Bridge over Curtis Creek
• Location:               Harrison Street east of South 24th.
• Timeline:               March 10 ‐ September 12, 2025
• Traffic Impact:     FULL CLOSURE
Details: Bridge replacement. New bridge to be wider and have sidewalks on both sides.

4. Prairie Crossings
• Location:               Prairie Crossings shopping center (61st & Broadway)
• Timeline:               April 8 ‐ August 1, 2025
• Traffic Impact:     Future closure of in-bound North 61st Street
Details: Pavement patching. Project is currently on hold due to material delays. One 
section of pavement remains.


5. South 18th Resurfacing - Harrison to Ohio
• Location:               South 18th from Harrison to Ohio
• Timeline:               July 7 ‐ August 22, 2025
• Traffic Impact:     Lane restrictions, side street closures.
                                   18th & Jefferson intersection to be closed for 2 weeks. Date TBD
Details: ADA sidewalk upgrades. Relocation of inlets & fire hydrant

6. South 48th & State—Adams County Project
• Location:               South 48th & State intersection and S 48th going south
• Timeline:               June 23 ‐ October, 2025
• Traffic Impact:     Closure of South 48th from State to Willow Creek
Details: Adding 4’ shoulder on both sides, curb & gutter and sidewalk on west side, culvert extension

UPCOMING PROJECTS (AWARDED / BIDDING)

 1. Broadway Water Main Replacement ‐ 24th to 30th
• Location:               Broadway between 24th and 30th Streets
• Timeline:               July 7 ‐ November 1, 2025
• Traffic Impact:     One lane open in each direction
Details: New water main, replacement of water service lines, some sidewalk replacement

2. 2025 Lead Service Line Replacement
• Location:              Chestnut to Riverview ‐ North 2nd to North 7th & other various locations
• Timeline:              June 1 ‐ December, 2025
• Traffic Impact:    Lane restrictions, streets to remain open
Details: Replacing lead water service lines to homes, sidewalk & pavement patching

3. College Street—North 4th to North 8th
• Location:              College St. from North 4th (US 24) to North 8th.
• Timeline:              July ‐ December, 2025
• Traffic Impact:    4th Street down to 1 lane, full closure of College
Details: Complete street replacement, new water main & services, sewer replacement

4. Cherry Street - North 24th to North 28th
• 
Location:               Cherry Street from North 24th to North 28th
• Timeline:               Bid opening: July 16, 2025
• Traffic Impact:     Full closure of Cherry
Details: Complete street replacement, new water main & services, sewer repairs

 